Calculate the concrete for a slab, footing, wall, beam or round column, and the bags of concrete mix or the cement, sand, gravel and water for it.

Enter the dimensions and the number of identical pieces, choose bagged concrete mix or a mix by volume such as 1:2:3, and add a small allowance for spillage and uneven ground. It works in US units or metric.

How it is calculated

Volume = length × width × thickness (or π × radius² × height) × pieces

The calculator first works out the volume of concrete. For a site mix by volume, the dry materials take up about 1.54 times the volume of the finished concrete, because the sand fills the gaps between the stones and the cement fills the gaps in the sand. That dry volume is split by the ratio: in a 1:2:3 mix, one part in six is cement, two are sand and three are gravel.

Cement is converted to weight at 1,440 kg per m³ (90 lb per ft³) and rounded up to whole bags; sand and gravel are shown as volume. The water is half the weight of the cement (a water–cement ratio of 0.5). Bagged concrete mix yields about 1 ft³ per 134 lb (1 m³ per 2,150 kg): an 80 lb bag makes about 0.6 ft³.

Example

A 10 × 10 ft patio slab 4 in thick is 10 × 10 × 4/12 = 33.3 ft³. With a 5% allowance that is 35 ft³, or 1.3 cubic yards: 59 bags of 80 lb concrete mix.

In metric: a 4 × 3 m slab 10 cm thick is 1.2 m³, or 1.26 m³ with 5% allowance. Mixed 1:2:3 it needs about 466 kg of cement (10 bags of 50 kg), 0.65 m³ of sand, 0.97 m³ of gravel and 233 liters of water.

Frequently asked questions

How many bags of concrete are in a cubic yard?

About 46 bags of 80 lb, 61 bags of 60 lb or 91 bags of 40 lb concrete mix; a cubic meter takes about 86 bags of 25 kg. For more than a cubic yard or so, ready-mix delivered by truck is usually cheaper and easier.

What does a 1:2:3 concrete mix mean?

One part cement, two parts sand and three parts gravel by volume, measured with the same bucket or shovel. Richer mixes such as 1:1.5:3 are stronger; leaner ones such as 1:3:6 are used under foundations and for fill. For structural work, follow the mix or strength your engineer specifies.

How much extra concrete should I order?

Add 5 to 10% for spillage, uneven ground and formwork that bulges. A little leftover concrete is much easier to deal with than running short halfway through a slab.